The following information is based on initial reviews of incident reports and should not be considered a comprehensive list of all incidents reported. The blog reports do not include sex crimes, domestic abuse, juvenile information, medical reports, and other sensitive police reports. The blog may differ from local news sources as well as trends reported at crimereports.com

Friday, May 10, 2013

#Fenway/ Muddy River Project update

The #Fenway/ Muddy River Project has provided us with the following information. Included is a work description and a schedule of the work. At this time the impact to Brookline residents appears to be minimal



Exploratory test pits will be dug on Brookline Ave between Riverway and Park Drive in order to locate a 12" & 48" water main which are to be relocated at a future date and to locate 51" & 45" drainage pipes which will be rerouted into the new future culvert. This work will be performed at night from 8:00 pm to 4:30 am. Brookline Ave will have single and double lane closures. There will be periods where Brookline will be shut down with traffic going inbound will be detoured to the Jug Handle and traffic outbound will be detoured around the Sears Rotary.

Schedule:



Monday 5/13 thru Thursday 5/16 - 8:00 PM to 4:30 AM



Traffic Impact:

Brookline Ave Inbound and Outbound between Riverway and Park Drive

Other Impacts



Temporary detours Inbound to Jug handle & Outbound around Sears Rotary



Mitigation:

State Police, Arrow Boards, Cones, Barrels, Detours